Key Experience of the firm
SN | Name of the Project | Work description | Name of the Client | Contract Amount (BDT) | Project Duration | Name of Firm consortium/As sociated if any | Qnt/. |
4. | Dhaka Mass Rapid Transit Development (MRT Line-1) |
| NKDOS Consortium Lead by Nippon Koei | 19,600,000 | February 2019 to December – 2019 | Consortium with Geomark Limited | 28km
Hatirjeel Shitalakha River 1200 Hector |
5. | Chittagong Water Supply Improvement
& Sanitation Project (CWSISP) |
| Chittagong WASA | 3,005,000 | February 2018 – March 2018 | In association with
with GPS & Hi- tech Engineering, | Chittagong City |
6. | Dohazari – Chawphaldandi road Development project |
| SMEC &
ACE consultants ltd. | 4,615,000 | January 2018 – February 2018 | In association with with GPS & Hi- tech Engineering, | 42 km |
7. | Dohazari – Cox’s Bazar – Gundam Dual-gauge Railway |
| SMEC & | 6,712,000 | January 2018 – | In association | 53 km |
SL | Name of the Project / Contract | Name of the Client | Project Duration | Quantity |
1. | Topographic Survey of Chittagong WASA | GPS & Hi-tech Engineering, Chittagong | February 2018 – March 2018 | Chittagong City |
2. | Geodetic control Survey, Traverse survey using RTK GPS for Road from Dohazari – Chawphaldandi | GPS & Hi-tech Engineering, Chittagong | January 2018 – February 2018 | 42 km |
3. | Geodetic control Survey, Traverse survey using RTK GPS for Railway line from Cox’sbazar- Chakaria | GPS & Hi-tech Engineering, Chittagong | January 2018 – February 2018 | 53 km |
4. | Geodetic control Survey, Traverse survey using RTK GPS for Railway line from Tongi-Akhaura | GPS & Hi-tech Engineering, Chittagong | November 2017- January 2018 | 102 km |
5. | Geodetic control Survey, Rail track survey, Traverse survey using RTK GPS for Railway line from Akhaura-Comilla | Max Infrastructure Ltd. | July 2017-November 2017 | 51 km |
6. | Geodetic control Survey, Rail track survey, Traverse survey using RTK GPS for Railway line from Akhaura-Comilla | Toma Construction & Co. Ltd | July 2017-November 2017 | 52 km |
7. | Topographical site survey three proposed Airport at Shriatpur, Munshigonj, and Manikgonj. using precise GNSS RTK. | Bangladesh University of Engineering and Technology (BUET) | March 2017-June 2017 | 150 sqkm |
8. | Geodetic control survey for Road construction project:
Gazipur-Alenga, Khulna-Mongla, Dhaka-Mawa, Kaua\ra kandi-Bhanga, Rajbari-Magura | Various survey company | January 2014-December 2016 | 210 km |
9. | Geodetic survey for small construction project:Cool power plant Rampal, Chittagong- Bashkhali Coal power Plant, JICA coal fired power plant-Matarbari | Various survey company | January 2014-December 2016 | 30 points |
10. | Geodetic Control survey for Railway construction project:Comilla-Chittagong, Gopalgonj_Kasiani, Iswardi-Sirajgonj, Dhaka-Narayangonj, Dhaka-Jamuna Bridge east, Khulna-Mongla | Bangladesh Survey OrganizationGPS Hi-tech
Land survey team | May 2014-November 2016 | 150 km |
11. | Geodetic & Bathymetrical survey ofMeghna, Lohalia, Bridhwar, Baleshwar, Kacha, Kirtonkhola, Arialkhan, Sandha, Modhumati Kaligonga, Putimari Ghoshikhali, Monga, Japjapia, Karulia and Kholpetua River
ESPA Delts (ecosystem Service for poverty alleviation) Project BUET | IWFM (BUET)
ESPA Delts (ecosystem Service for poverty alleviation) Project BUET | February 2014-May 2014 | 250 section |
12. | 52 Geodetic Control survey for geo-referencing of 0.6 m Satellite Imagery of 725 skm preparing ortho rectification and stereo plotting.Physical Feature survey work with RTK GPS, Total station & using 3D image and other Survey for area of
Preparation of Development plan for Beanpole-Jessore High way Corridor project” | Urban Development Directorate (UDD) | April 15 2014- June 30 2014 | 220 hector |
13. | Topographical Survey and contour mapping, Geodetic survey. Earth volume calculation, Boundary Demarcation ofRampal Tharmal power plant project | Bangladesh–India Friendship Power Company (Pvt.) Limited | January 2014- February 2014 | 70 hector |
14. | Geodetic survey for Cadastral MappingDirectorate of Land Records & Surveys | Directorate of Land Records & Surveys | February 2013- April 2013 | 45 points |
15. | Geodetic survey for Cadastral mappingDirectorate of Land Records & Surveys | Directorate of Land Records & Surveys | February,2012-May 2012 | 50 points |
16. | Geodetic Control surveyVarious small scale project | Geomark Limited,Bangladesh Survey organization (BSO) | June 2012 -December 2012 | 60 hector appro. |
17. | Topographical Survey (infrastructure, physical feature survey and geodetic survey under“Upazila Town infrastructure Development Project” Comilla | Sheltech (pvt) Ltd(Bangladesh) | Jun 2008 – January 2011 | 12 upazias |
18. | Topographical Survey (infrastructure, physical feature survey and geodetic ) under “Upazila Town infrastructure Development Project” Faridpur | Development Design Consultants Ltd (DDC) (Bangladesh) | April 2008 – January 2011 | 9 upazilas |
19. | Control survey, Traverse survey, BM pillar construction Topographical Survey for river training work at North bankPadma Multipurpose Bridge project | MAUNSELLAECOM
nhc | Feb 2010-May 2010 | 4 sqkm |
20. | Topographical Survey for digital modelingAnd Geodetic control survey of approach road .
Padma Multipurpose Bridge project | MAUNSELLAECOM
nhc | June 2009-August 2009 | 26 km |
21. | Topographical Survey, Video capturing and photographyProposed Express Elevated Highway
Dhaka, Bangladesh | R & R Holdings | Oct 2009 – Oct 2009 | 32 km |
22. | Topographical survey with 1m contour of“Taunhinbon Hydro Power Project”Laos | AAM Survey (Thailand) | Jan 2007 – Mar 2008 | 350 sqkm |